HomeMy WebLinkAboutSupplemental TestimonySUPPLEMENTAL WRITTEN TESTIMONY OF
FERTILE GROUND CONSERVANCY
In the Matter of: Appeal of Planning Director's Decision
Applications: PDF 25-01 (Final PUD) and SDR 25-02 (Standards Review)
Braewood Hills 3rd Addition — Tax Lot 18-04-11-12 / 00200
Eugene, Oregon
Submitted to: David Doughman, Hearings Official
Via: Nick Gioello, Associate Planner (ngioello@eugene-or.gov)
Date: May 6, 2026
I. INTRODUCTION AND STANDING
Fertile Ground Conservancy (FGC) is a 501(c)(3) land trust dedicated to the protection and defense of wild
places in the Cascadia region, with a specific conservation focus on waterways, wetlands, riparian corridors,
and associated listed-species habitat. FGC submitted written testimony in this proceeding on April 29, 2026,
and has standing as an organization that submitted written comments in the original proceeding (EC
9.7605(1)(d)) and is adversely affected by the proposed development's impacts on Videra Creek, a tributary
of Amazon Creek and the Long Tom River within FGC's primary conservation area (EC 9.7605(1)(f)).
This supplemental submission raises additional arguments based on FGC's review of the Planning
Commission's Final Order on the Tentative PUD appeal (PDT 24-1 / ST 24-3, February 18, 2025) and
newly received regulatory documentation from the U.S. Army Corps of Engineers, attached as Exhibit A.
II. THE FINAL PUD RECORD DOES NOT DEMONSTRATE CONFORMANCE WITH
BINDING TENTATIVE PUD CONDITIONS
Under EC 9.8365(1), the final PUD plan must conform with the approved tentative PUD plan and all
conditions attached thereto. The Planning Commission's February 18, 2025, Final Order imposed 27
conditions of approval on the Tentative PUD. FGC submits that the Final PUD record does not appear to
demonstrate conformance with at least three of those conditions.
Condition 18 (verbatim): "Prior to final PUD approval, the applicant shall obtain Type II Standards
Review approval for the proposed public street extension of Randy Lane and any other utility crossings or
other allowed improvements within the protected /WR conservation area, subject to the applicable standards
at EC 9.4900–9.4980."
Condition 18 is a condition precedent: it requires that the Type II Standards Review approval — subject to
the EC 9.4900–9.4980 /WR Water Resources Conservation Overlay standards, for the Randy Lane
extension and any other crossings or allowed improvements within the /WR conservation area — be
obtained before the Planning Director could issue Final PUD approval. The operative question is binary: is
the Type II Standards Review approval decision in the record, and is it dated prior to the Final PUD
approval? If the Final PUD record does not contain the Standards Review decision, conformance with
Condition 18 has not been established. FGC's understanding from the April 22, 2026, staff memorandum
is that /WR construction-practice compliance for the /WR-area improvements was not fully demonstrated
on the public record at this stage and instead was anticipated to be addressed through a Performance
Agreement. Regardless, the dispositive question for Condition 18 is whether the Type II Standards Review
decision exists in the record and predates the Final PUD decision.
Condition 19 (verbatim): "All future building permits for Lots 30 through 35 shall depict the Goal 5
resource and its 40-foot setback from top of bank and shall include site plans showing the location of
protective fencing subject to the applicable standards at EC 9.4920–9.4930."
Condition 19 fixes the operative protective setback for the Goal 5 stream resource at 40 feet from the top
of bank for Lots 30–35 — the lots closest to the protected stream corridor — at the building permit stage.
This is consistent with EC 9.4920(1)(c), which establishes a 40-foot conservation setback from the top of
high bank for Category C streams. The Final PUD plans must not conflict with this setback treatment. FGC
requests the Hearings Official confirm that the Final PUD plans are consistent with Condition 19 and that
the Goal 5 resource and 40-foot setback are correctly depicted and not contradicted.
Condition 22 (verbatim): "No site alteration is allowed prior to final PUD approval. This prohibition
includes site grading and the removal of trees and other vegetation, as well as any impacts to wetlands and
the protected stream on the subject property including changes to the existing drainage pattern. Any such
alterations shall only be allowed subject to permit review and approval, and erosion control measures as
required for the proposed work."
Condition 22 prohibits site grading, vegetation removal, wetland impacts, and drainage alteration prior to
final PUD approval. EC 9.7630(3) provides that the action of the appeal review authority is final. Because
the Hearings Official has not yet issued a decision on this appeal, the final city-level action on the Final
PUD is not yet complete. There is a strong argument that "prior to final PUD approval" in Condition 22
means prior to the Hearings Official's ruling. FGC recognizes the City portal may display an effective date
for the Planning Director's decision; Condition 22 is keyed to "final PUD approval," and EC 9.7630(3)
makes the appeal review authority's action the final city-level action. Any site grading, clearing, wetland
disturbance, or drainage alteration before that ruling may violate a binding condition of the Tentative PUD
approval, depending on how 'final PUD approval' is interpreted in Condition 22. FGC requests that this
question be addressed on the record and that the applicant be notified of Condition 22's continued
applicability during the pendency of this appeal.
III. GOAL 5 WETLAND SETBACKS UNDER EC 9.4920 — AMA-5A AND AMA-5B
The City's adopted Goal 5 Water Resources Conservation Plan ESEE Conclusions Summary Table
identifies wetland sites in the Videra Creek and Hawkins vicinity. Specifically: AMA-5A ("West Eugene
Uplands wetland at Videra Ck," 0.16 acres) is designated Category B Wetland, Limit Conflicting Uses,
with a 25-foot conservation setback. AMA-5B ("West Eugene Uplands wetland at Videra Ck," 1.00 acres)
carries the same designation. AMA-4 ("West Eugene Uplands wetland at Hawkins," 1.44 acres) is
designated Fully Allow Conflicting Uses with no setback.
To the extent any of the delineated wetland features on Tax Lot 18-04-11-12 / 00200 correspond to AMA-
5A or AMA-5B — or any other Category B wetland designation under the City's adopted Goal 5 program
— EC 9.4920(2)(b) requires a 25-foot conservation setback measured from the jurisdictional wetland
boundary. This setback operates independently of the stream setback established by Condition 19. Where
a Category B wetland setback applies, the /WR conservation area is the union of the stream setback footprint
and the wetland setback footprint, consistent with the combined-footprint framework of EC 9.4920(3): any
area within 25 feet of the AMA-5A or AMA-5B boundary is within the /WR conservation area regardless
of its distance from the stream.
FGC requests that the record confirm which, if any, of the delineated on-site wetland features correspond
to AMA-5A, AMA-5B, or AMA-4, and that the Final PUD plans reflect the applicable setbacks
accordingly. The record does not appear to include a combined setback analysis — specifically, a plan sheet
or exhibit showing both the 40-foot stream setback line and any applicable Category B wetland setback
line(s) — addressing both the Goal 5 stream setback and any applicable Goal 5 wetland setbacks
independently.
IV. USACE APPROVED JURISDICTIONAL DETERMINATION — WETLAND 2B
FGC recently received an Approved Jurisdictional Determination (AJD) issued by the U.S. Army Corps of
Engineers, Portland District, dated July 25, 2025 (reference: CENWP-ODG, NWP-2022-30), attached as
Exhibit A. The AJD identifies Wetland 2B on the subject property as a federally jurisdictional Waters of
the United States. According to the AJD, all other delineated wetland features on the property were
determined to be non-jurisdictional.
This AJD post-dates the City's Tentative PUD approval process and was not part of the analytical baseline
on which prior approvals relied. The federal jurisdictional status of Wetland 2B means that any fill or
disturbance of that feature requires a Section 404 permit from the Corps of Engineers. FGC has not located
evidence in the City record that the applicant has obtained a Section 404 authorization for any proposed
disturbance of Wetland 2B, and requests the applicant and City identify whether such authorization exists
and how the jurisdictional status of Wetland 2B is being incorporated into the project's avoidance,
minimization, and permitting posture.
V. REQUESTS
FGC respectfully requests that the Hearings Official:
(1) Confirm on the record whether a Type II Standards Review approval under EC 9.4900–9.4980 was
obtained and is documented in the record prior to the Planning Director's Final PUD decision. If it is not,
reverse or remand the decision on that basis.
(2) Confirm whether any on-site wetland features are designated Category B wetlands under the City's
adopted Goal 5 program, and if so, confirm that the 25-foot conservation setback required by EC
9.4920(2)(b) is reflected in the Final PUD plans and does not conflict with them.
(3) Address on the record whether Condition 22's site alteration prohibition applies during the pendency of
this appeal, and if so, notify the applicant accordingly.
(4) Accept Exhibit A (USACE Approved Jurisdictional Determination, CENWP-ODG, NWP-2022-30,
July 25, 2025) into the record and direct the applicant and City to confirm the permitting posture with
respect to Wetland 2B.
Respectfully submitted,
Dillon Thomson
Executive Director, Fertile Ground Conservancy
PO Box 11262, Eugene, OR 97440
info@fertilegroundconservancy.org
541-515-7747
Exhibit A: U.S. Army Corps of Engineers Approved Jurisdictional Determination, CENWP-ODG, NWP-
2022-30, dated July 25, 2025 (attached)