Please check one of the following:
Adjustment Review, Minor
Adjustment Review, Major
Code Interpretation
Hazardous Materials Review
Historic Property Alteration
Historic Property Demolition
Historic Property Move
Modification of a Conditional Use Permit
Modification of a PUD Tentative
Modification of a PUD Final
Modification of a Site Review
Modification of a Standards Review
Modification of a Subdivision Plan
Modification of a Willamette Greenway
Partition Tentative
Partition Final
PUD Final
Site Review
Standards Review
Subdivision Tentative
Subdivision Final
Traffic Impact Analysis
Vacation Improved Public R‐O‐W
Vacation Improved Public Easement
Unimproved Public R‐O‐W with Re‐dedication
Variance
APPEAL OF PLANNING DIRECTOR DECISION
This appeal form applies to appeals of interpretation of this Land Use Code made according to EC 9.0040(1) and to
appeals to all Type II land use applications. The appeal of the Planning Director’s decision provides for a review of an
administrative decision by a higher review authority specified in this Land Use Code. The Planning Director’s decision
may be affirmed, reversed, or modified.
City File Name:_______________________________________________________________________________________________
City File Number:_____________________________________________________________________________________________
Date of Planning Director Decision:______________________________________________________________________
Date Appeal Filed:___________________________________________________________________________________
(This date must be within 12 days of the date of the mailing of the Planning Director’s decision.)
Attach a written appeal statement. The appeal statement shall include a written statement of issues on appeal and
be limited to the issues raised in the appeal. The appeal statement shall explain specifically how the Planning
Director’s decision is inconsistent with applicable criteria. Please contact Planning staff at the Permit and
Information center, 99 West 10th Avenue, 541‐682‐5377, for further information on the appeal process.
A filing fee must accompany an appeal of a Planning Director decision, with some exceptions for neighborhood
groups. The fee varies depending upon the type of application and is adjusted periodically by the City Manager.
Check with Planning staff at the Permit and Information Center to determine the required fee or check on the web
at: www.eugeneplanning.org
March 27, 2026
Mr. Nick Gioello, Associate Planner
City of Eugene Planning Division
99 W. 10th Ave, Suite 290
Eugene, OR 974012
Via email: ngioello@eugene-or.gov; planning@eugene-or.gov
Re: Appeal Statement: Braewood Hills 3rd Addition, Final PUD (PDT 25-01) & Standards Review (SDR 25-02)
Save Videra Oak Meadows and Wes Van Winkle (“Clients”) provides the following appeal statement on
the Planning Director’s Decision on Braewood Hills 3rd Addition final planned unit development (“PUD”) and
standards review applications (“Final PUD” and “SDR,” respectively), File Nos. PDT 25-01/ST 25-02
(collectively, “Applications”). The Planning Director’s Decision (“Decision”) has numerous errors precluding
approval of the Applications.
For the following reasons, the Decision should be reversed, and the Applications for the final planned
unit development and standards review denied.
I. Appeal T imeliness
The Decision was signed by the Planning Director on March 12, 2026, with the mailing of the Decision
occurring on March 17, 2026. This Appeal is being filed on March 27, 2026, along with the required filing fee,
and therefore, this appeal complies with EC 9.7605.
II. Final Planned Unit Development (PDF 25-01)
The Applicant has failed to comply with the applicable provisions for a final PUD, and the Decision errs
in approving the application.
1. The Decision contradicts the Fire Marshal’s review and errs in finding compliance with
EC 9.8365
Public comments on the file’s documents noted numerous problems with access to the site by
emergency vehicles, including narrow private streets and driveways, excessively steep grades, and other issues.
3/27/2026
2
The Decision responds to these concerns by stating that the Fire Marshal’s Office reviewed the final
PUD and earlier iterations of the PUD and subdivision and “expressed no concerns related to emergency service
access to the site.” Decision, p. 2. In a specific response to public comments regarding the driveways being too
narrow for emergency vehicle access, the Decision states that the Fire Marshal provided referral comments
“which did not express concerns with the driveway widths or indicate a risk to public safety.” Decision, p. 4.
These statements in the Decision are false.
Attachment A to the Decision is a two-page document consisting of comments and conditions by the
Fire Department which flatly contradict the Planning Director’s statements.. For example, point 1 of the Fire
Marshal’s comments states:
1. The maximum street profile slope for Tambour Court has changed from the PDF-24-01 to the PTF-
25-01 from a maximum slope of 19% to 24%. This is not acceptable for fire apparatus access.
(Emphasis added.) Show a revied (sic) profile with maximum slope of 20% with transitions to 10%
on each side.
This is especially troubling as this represents a modification, a significant change, to the original
approval of the tentative PDF, which would necessarily require a new or modified tentative PUD application.
This change is expressly noted by the Fire Marshal as problematic with respect to fire apparatus access. With
the increased risk of wildfire in Eugene, this potential handicap to fire response endangers not just this proposed
development, but the existing residences in the surrounding area. This change which the Decision fails to
address represents a danger to the health and safety of the community.
This modification violates EC 9.8365(1), which provides:
“The planning director shall approve, approve with conditions, or deny a final PUD application,
based on compliance with the following criteria:
(1) The final PUD plan conforms with the approved tentative PUD plan and all conditions
attached thereto.”
3/27/2026
3
As the final PUD plan does not conform to the approved tentative PUD plan, the Applicant has failed to
demonstrate compliance with EC 9.8365(1), and therefore, the Decision should be reversed and the PDF
application denied.
Similarly, point 2 of the Fire Marshal’s comments notes:
2. Street widths of 21 feet with parking on one side appear to meet City of Eugene engineering
standards for local public access However, Eugene Springfield Fire strongly recommends following
the 2022 Eugene Fire Code, Section 503.2.1 which requires 20 feet clear width with no parking
allowed on both sides withing that 20-foot width for these private streets. “NO PARKING FIRE
LANE” signage shall be posted on both sides of the Randy Lane, Tambour Lane, and Tambour
Court (2022 Eugene Fire Code Section D103.6).
Point 4 of the Fire Marshal’s comments states:
4. Several lots show access to be provided by 10-and 14-foot-wide utility and access easements. This
width will not be adequate for the required fire apparatus access requirements of 20’ minimum.
(Emphasis added.) Access requirements will be evaluated at the time of building permit submittal,
when such access is proposed (2022 Eugene Fire Code 503.2.1).
Each of the Fire Marshal’s quoted comments contradict the Decision and support the public comments
arguing that the development plan is a fire hazard and poses a threat to public safety. The roads and, in
particular, the driveways are inadequate for access by fire apparatus. These flaws are especially grave in view
of the fact that the entire project is essentially designed as a cul de sac and naturally existing fire-resistant
features of the property, such as the majority of the wetlands and Oregon oak trees, are proposed to be
removed. These deficiencies must be addressed and rectified.
In sum, the Decision erred in finding compliance with EC 9.8365(1) as the Applicant has not carried
their burden of proof by providing evidence of compliance, instead providing evidence of impermissibly
changing the approved tentative PUD.
III. Standards Review (SDR 25-02)
A. The Applicant has not demonstrated compliance with EC 9.4980(4)(a)
3/27/2026
4
EC 9.4980(4) provides:
“Construction Practices. Construction within the / WR conservation area, and within
areas removed from the / WR conservation area shall comply with the following
standards:
a) For purposes of this subsection, heavy machinery is defined as motorized or
mechanized machinery or equipment capable of deliberately or inadvertently
damaging vegetation, or damaging or compacting soil. The following standards
shall apply to use of heavy machinery within the / WR conservation area:
1. On sites where soils are susceptible to severe compaction or structural damage
when wet or saturated, use of heavy machinery shall be limited to the period
between June 15 and September 30, unless otherwise approved by the
planning director.
2. Use of heavy machinery shall be the minimum necessary for the use or activity
and shall be restricted to those areas where its use is necessary.”
With respect to compliance with this provision, the Decision states:
“The applicant' s plan does not show staging locations for machinery, and provides no explanation
in the written statement, likely due to the fact that the construction will utilize the proposed road
as the access for the site which is mostly located outside of any Conservation Area. However,
without that clarity in the record, the following conditions are warranted to minimize impacts to
areas that do not need to be impacted by heavy machinery to construct the street and stormwater
facility:
5. Prior to final site plan approval, the applicant shall submit a revised site plan that shows
staging area( s) for heavy machinery. Alternatively, the applicant may include a note on
the final site plan stating, ‘No staging areas for heavy equipment will be located within a
Conservation Area.’
6. Prior to final site plan approval, the applicant shall submit a revised site plan that shows
the location of access for and use of heavy machinery within the extent of the
Conservation Area impacted by the construction of the road.
7. Prior to final site plan approval, the following note shall be added to the final site plans:
Heavy machinery may only be used in the / WR conservation areas between .tune 15
and September 30 and will not be used outside of the area shown on this site plan for
staging and access to the construction impact area.
Based on these findings and conditions, the above standards are met.”
Decision, p. 15.
First, the Decision recognizes that the Applicant failed to provide evidence of compliance. Second, by
including the word “alternatively” the Decision contradicts itself with regard to Condition of Approval 7 which
requires a note on the site plan referring to areas that are designated as the staging areas for heavy equipment.
Providing a note that allows the Applicant not to designate staging areas on the site plan renders the conditions
of approval insufficient to ensure compliance with the provision. Regardless, without the actual evidence of
3/27/2026
5
where the heavy equipment will be staged, it is impossible to state that the Applicant has complied with this
provision.
Additionally, the Decision notes that the Applicant has proposed fencing along the Conservation Area,
north of the road, but fails to address the lack of protective fencing proposed along the Conservation Area south
of the road. Here, again, the Applicant has failed to provide evidence of compliance.
Therefore, the Decision erred in finding compliance with EC 9.4980(4)(a) as the Applicant has not
carried their burden of proof by providing evidence of compliance.
B. The Applicant has not demonstrated compliance with EC 9.4980(4)(b)
EC 9.4980(4)(b) provides:
“Petroleum products, chemicals, or other deleterious materials used in the construction process
shall not be allowed to enter a stream or wetland that is within a /WR conservation area.”
With respect to compliance with this provision, the Decision states:
“The applicant provides a statement that agrees to the above criterion, however evidence to
demonstrate how their plan will comply is not provided. To ensure compliance with this
standard, the following condition is warranted:
8. Prior to final site plan approval, the applicant shall add a note to the final site
plans that states, " Petroleum products, chemicals, or other deleterious materials
used in the construction process shall not be allowed to enter a stream or wetland
that is within a WR conservation area.’
Based on the materials in the record and the above findings and conditions of approval, the
standards at EC 9.4980(4) are met.”
Decision, p. 15.
First, the Decision recognizes that the Applicant failed to provide evidence of compliance. Second,
adding the language of the provision to the final plat in no way actually provides any evidence that ensures
compliance with this provision. Sinply restating the provision is not evidence of compliance.
Therefore, the Decision erred in finding compliance with EC 9.4980(4)(b) as the Applicant has not
carried their burden of proof by providing evidence of compliance.
IV. Conclusion
3/27/2026
6
For the above reasons, Save Videra Oak Meadows and Wes Van Winkle requests that the Decision on
the final PUD and the standards review applications, File Nos. PDT 25-01/ST 25-02, should be reversed and
denied.
Respectfully submitted,
Charles W. Woodward, IV
Attorney for Save Videra Oak Meadows and Wes Van Winkle