October 3, 2025
Carol Schirmer
Schirmer Consulting, LLC
PO Box 10424
Eugene OR, 97440
RE: Braewood Hills Third Addition (PDF 25-1 & SDR 25-2)
Thank you for the application materials submitted for Final Planned Unit Development. Based on
staff review, the application is deemed incomplete. Please address the following conditions of
approval:
COA#5: Prior to final PUD and plat approval, the applicant shall submit Private Joint Use
Access and Utility Easement and Maintenance Agreement (JAM). The JAM will include a
description defining the area of the private street and will also identify permitted
improvements, construction expectations, rights of usage and maintenance responsibilities
for the facilities in the street. The JAM will be recorded concurrent with and cross - referenced
on the final plat.
At the time of this review no Joint Use Access and Utility Easement and Maintenance
Agreement (JAM) has been submitted for review, therefore this condition is not satisfied.
COA#6: Provisions for a public emergency access easement within the private street may be
included in the proposed JAM which creates the private street, or alternatively, may be
dedicated as a Public Emergency Access Easement on a standard City form.
At the time of this review no JAM has been submitted, therefore this condition is not satisfied.
COA#7: Prior to final plat approval, the applicant shall dedicate a 14 -foot Public Utility
Easement or Public Wastewater Easement that will encumber the proposed public
wastewater system. The required easement shall also be shown on revised final PUD plans.
The Final PUD plans do not show a 14-foot PUE or Public Wastewater Easement to encumber
the proposed public wastewater system, therefore this condition is not satisfied.
COA#16: The location of proposed Joint Access Easements shall also be clearly shown and
labeled as such on final PUD plans.
All proposed Joint Access Easements are clearly shown on the final PUD plans, with the
exception of the easement over Lots 4-5 & 9-10, therefore this condition is not satisfied.
COA#26: Prior to final PUD approval, the applicant shall submit updated application materials
that demonstrate compliance with EC 9.6796.
The updated stormwater report notes that all proposed stormwater facilities will be publicly
owned, however, no public stormwater easements are proposed, therefore this condition is not
satisfied.
Staff have also reviewed the concurrent Standards Review application and have no issues with it,
however, it will remain incomplete until the issues described above with the Final Planned Unit
Development application have been addressed.
If you have any questions, please contact me,
Sincerely,
Nicholas R. Gioello
Associate Planner