Loading...
HomeMy WebLinkAboutFinal Order (2)Ams"MPIN-0, • Planning Commission FINAL ORDER OF THE EUGENE PLANNING COMMISSION ON REMAND FROM THE OREGON LAND USE BOARD OF APPEALS: CAPITAL HILL PUD (PDT 17-1) INTRODUCTION This final order concerns a remand by the Oregon Land Use Board of Appeals of the Eugene Planning Commission's decision approving the tentative planned unit development (PUD) application for the proposed Capital Hill PUD (PDT 17-1). The subject property is 13.63 acres in size and is developed with multiple residences and accessory buildings. Located south of Hendricks Park, at the end of Capital Drive, the entire property is zoned R-1 Low Density Residential, and a portion has the /PD Planned Unit Development Overlay. The applicants, Cynthia and Thomas Dreyer, filed an application for a tentative PUD to create a 34-lot residential subdivision. The Eugene Hearings Official held the initial public hearing on the tentative PUD application on March 7, 2018. Following the hearing and open record period for additional testimony, on April 20, 2018, the Hearings Official approved the tentative PUD application with 20 conditions of approval. On May 7, 2018, both the applicant and the Joint Response Committee of the Fairmount Neighbors Association and Laurel Hill Valley Citizens (Joint Response Committee) timely filed appeals of the Hearings Official's decision. On May 9, 2018, the City mailed written notice of the appeals. The Planning Commission held a public hearing on the appeals on May 22, 2018. The Planning Commission deliberated on the appeal issues at its meetings on June 4, 7, and 12, 2018, and reached its final decision on June 14, 2018. The Planning Commission affirmed the Hearings Official's approval of the tentative PUD, with additional findings and conditions as well as modifications to certain conditions of approval imposed by the Hearings Official. Specifically related to this remand, the Planning Commission modified Condition of Approval #10 to require that additional geotechnical analyses required for building and infrastructure permits address potential off-site impacts. Both the applicant and the Joint Response Committee timely appealed the Planning Commission's decision to the Oregon Land Use Board of Appeals (LUBA). LUBA affirmed the majority of the Planning Commission's decision, but ultimately remanded to allow the Planning Commission to adopt more adequate findings based on substantial evidence, regarding Final Order: Capital Hill PUD (PDT 17-1) Remand Page 1 The applicant appealed LUBA's decision to the Court of Appeals, and on February 27, 2019 the Court of Appeals affirmed LUBA's decision without opinion. On May 7, 2019, the applicant requested that the City begin to process the remand. On May 19, 2019, Planning staff mailed a "Notice of Opportunity to Submit Written Testimony to the Eugene Planning Commission - Limited Issues" to the applicant and interested parties. The notice provided that the Planning Commission would accept "written testimony that addresses the Capital Hill Tentative PUD application's compliance with the geotechnical requirements of Eugene Code (EC) sections 9.8320(6) and 9.9630(3)(c)." The City intentionally limited the scope of permissible new testimony to testimony that is relevant to the scope of issues set out in LUBA's remand. The Planning Commission did not hold a hearing on remand. The Planning Commission held deliberations on the remand on August 6 and 13, 2019. 1 Although LUBA's remand references EC 9.9630, that code section does not apply directly to this tentative PUD application. EC 9.9630 only applies to applications for subdivisions, partitions and site review. See EC 9.9500. However, the policies of the South Hills Study that are codified in EC 9.9630 are directly applicable to the tentative PUD application through EC 9.8320(2) ("The PUD is consistent with applicable adopted refinement plan policies."), so the application must comply with the same substantive approval criteria included in EC 9.9630(3). This Final Order will therefore refer to the applicable South Hills Study policy rather than to EC 9.9630. Final Order: Capital Hill PUD (PDT 17-1) Remand Page 2 I1® RECORD ET PLANNING COMMISSION III® ISSUES PROCEDURAL Bias/Ex arte Contacts At the Planning Commission meeting on August 6, 2019, Vice Chair Tiffany Edwards responded to a letter dated June 18, 2019 from Sean Malone requesting that Commissioner Edwards recuse herself from the decision on remand. The Malone letter alleged that a 2018 email exchange between Commissioner Edwards (who was not a planning commissioner at the time) and a representative of the applicant constitutes an ex parte contact and shows that Commissioner Edwards is biased. Regarding the allegation of ex-parte contact, Commissioner Edwards confirmed that at the time of the email in question she was not a Planning Commissioner so her contact with the applicant's representative did not constitute an ex parte contact. Regarding the allegation of bias, Commissioner Edwards stated that she could make an unbiased decision on the application and was able to set aside her personal views to evaluate the application based solely on the evidence and argument in the record and the applicable approval criteria. Rejection of Testimony At the Planning Commission meeting held on August 6, 2019, the Planning Commission rejected the following testimony submitted during the remand open record period: 1. The Planning Commission rejected Susan Ferris' June 12, 2019 letter because it was outside of the scope of the open record on remand, except for the following testimony: ® The first sentence of paragraph 1, beginning with "Eugene Code (EC) Sections..." and ending with "...residential lots in this area."; ® The portion of the fourth sentence in paragraph 5 that states "This area suffers from erosion"; ® Paragraph 6; ® The first sentence in paragraph 8 and the phrase "problems with erosion"; ® The first sentence of the final paragraph; and ® Closing salutation 2. The Planning Commission rejected the fourth and fifth paragraphs of Jennifer Mackey's June 18, 2019 email because the Planning Commission determined that they were outside of the scope of the open record on remand. Final Order: Capital Hill PUD (PDT 17-1) Remand Page 3 3. The Planning Commission rejected the third and fourth sentences of the third paragraph on the second page of Nathaniel Teich's June 18, 2019 letter because the Planning Commission determined that they were outside of the scope of the open record on remands The Planning Commission has limited its consideration of the issues on remand to the remand issues identified by LUBA's Final Opinion and Order, dated November 20, 2018, for LUBA Nos. 2018-074 and 2018-080. IV. FINDINGS F FACT A CONCLUSIONS F LAW After consideration of the applicable law and all argument and evidence in the record, the Planning Commission readopts its Final Order dated June 14, 2018, as amended and supplemented below. Specifically, the Planning Commission finds that the subject application complies with EC 9.8320(6) and the South Hills Study's specific recommendations for development standards related to review of on-site and off-site impact of the development. In the event of any conflict between this Final Order and the initial Planning Commission decision on this application or the Hearings Official's decision on this application, this Final Order shall prevail. The Planning Commission's June 14, 2018, decision is adopted by reference and included as Attachment A. The Hearings Official's decision is adopted by reference and included as Attachment B. Applicable Approval Criteria on Remand LUBA's remand focused on two approval criteria: EC 9.8320(6) and the specific recommendations from the South Hills Study for development standards related to review of on-site and off-site impact of the development.z 2 As noted above, LUBA's remand refers to EC 9.9630(3)(c) rather than the South Hills Study. EC 9.9630 does not apply directly to this tentative PUD application. EC 9.9630 only applies to applications for subdivisions, partitions and site review. See EC 9.9500. However, the specific recommendations from the South Hills Study for development standards related to on-site and off-site impact of development that are directly applicable to this application are identical to EC 9.9360(3)(c) - the code section LUBA referenced in the remand. Final Order: Capital Hill PUD (PDT 17-1) Remand Page 4 EC 9.8320(6) provides: The FIJD will not be a significant risk to public health and safety, including but not limited to soil erosion, slope failure, stormwater or flood hazard, or an impediment to emergency response. EC 9.8320(2) requires that the PUD be consistent with applicable adopted refinement plan policies. The Planning Commission has previously determined that the South Hills Study is an adopted refinement plan applicable to the subject property. The South Hills Study's specific recommendations for development standards related to review of on-site and off-site impact of the development require the following: That adequate review of both on-site and off-site impact of any development by a qualified engineering geologist occur under any of the following conditions: 1. ,411 formations: Soil depth of 40 inches and above. Slopes of 30 percent and above. 2. Basalt flows: Soil depth of 40 inches and above. Slopes of 20 percent to 30 percent. 3. Eugene Formation: Soil depth of 40 inches and above. Slopes of 20 percent to 30 percent. 4. Basalt flows: Soil depth of 20 to 40 inches. Slopes of 30 percent and above. 5. Eugene Formation: Soil depth of 20 inches to 40 inches. Slopes of 30 percent and above. Remand issue #1: Significant Risk to Public Health and Safety and On-Site Impacts LUBA's Final Opinion and Order Regarding the issues of on-site impacts of the proposed development and significant risk to public health and safety from slope failure and soil erosion, LUBA explained: In our view, a reasonable decision maker would not have relied upon the [applicant's] Geotechnical Investigation to find compliance with EC 9.8320(6) and EC 9.9630(3)(c). We conclude this based in part on the apparently unrebutted expert testimony of the Neighbors' consultant that no reliable conclusions can be drawn regarding potential for slope failure on the site, based on test pits clustered on the least steep portion of the property, encompassing only 20 percent of the property, and some distance from two identified areas of soil Final Order: Capital Hill PUD (PDT 17-1) Remand Page 5 instability on which development is proposed. Our conclusion is also based on the unexplained assumption that the test pit locations are representative of the subsurface conditions on the remainder of the property. LUBA Final Opinion and Order dated November 20, 2018, LUBA Nos. 2018-074 and 2018-080, slip op at 38-39. Planning Commission's Determination The applicant has submitted the following Geotechnical reports, which have been signed and stamped by Ronald J. Derrick, P.E., G.E. and Gary Sandstorm C.E.G.: In response to LUBA's remand, the applicant submitted a supplemental geotechnical/geologic report entitled: "Geotechnical/Geologic Investigation RE: LUBA Remand" which was signed and stamped by Ronald J. Derrick, P.E., G.E. and Gary Sandstorm C.E.G. and dated May 14, 2019. The applicant also submitted a Technical Memorandum regarding City of Eugene Stormwater review applicability, dated July 8, 2019, and signed and stamped by registered professional engineer Nathan Patterson. In response to LUBA's comments on remand, on March 22, 2019, the applicant excavated nine additional test pits on the site. The applicant then submitted a supplemental Geotechnical Investigation dated May 14, 2019. In that supplemental report the applicant states that the "test pits were not arranged in a manner to maximize a certain percentage of the site area, but rather in accordance with engineering practices and the City of Eugene Standards for Geological and Geotechnical Analysis." The City's Standards for Geological and Geotechnical Analysis are adopted in Administrative Order No. 58-02-25-F. The Planning Commission recognizes that the standards of Administrative Order No. 58-02-25-F are not directly applicable to this tentative PUD application.' Nevertheless, the Planning Commission finds that Administrative Order No. 58-02-25-F provides a useful guide to the requirements for geotechnical evaluations, and specifically the adequacy of test pit locations, and provides helpful context regarding the question of whether the applicant's geotechnical evaluation can be relied upon to determine the application's consistency with EC 9.8320(6) and the applicable geotechnical recommendations from the South Hills Study. City Public Works staff has opined that the placement and quantity of the applicant's test pits (including the nine new test pits) meet the minimum requirements in Administrative Order No. 58-02-25-F for 3 Administrative Order No. 58-02-25-F sets out specific requirements for geotechnical evaluations subject to compliance with EC 9.6710. Those standards are not directly applicable in the case of Capital Hill PUD due to its inclusion on the City's Goal 5 inventory - see EC 9.6710(3)(f) (activities on land included in the City's acknowledged Goal 5 inventory are exempt from the requirements of EC 9.6710). Final Order: Capital Hill PUD (PDT 17-1) Remand Page 6 number and spacing of test pits. The Planning Commission therefore finds that the applicant has provided the City with substantial evidence that the location of the test pits adequately identify the geologic features of the site. The applicant's May 14, 2019 Geotechnical Investigation identifies an area of previous slide activity on the northeastern portion of the site as well as possible past landslide activity in the southeast portion of the site. However, the applicant's experts did not observe any signs of recent or active landslide activity. The applicant's May 14, 2019 Geotechnical Investigation concludes that "[n]ew landslide activity is not expected, provided that primary landslide triggers are mitigated during the site development. These triggers are: removing material from the base of a slope or toe, adding surcharge loads to the top of a slope, and increasing water infiltration into existing landslide mass." The applicant's May 14, 2019 Geotechnical Investigation reiterates the recommendations in the applicant's February 6, 2017, Geotechnical Investigation and includes the following additional recommendations: 1. Control the input of water onto slopes within the moderate and deep landslide susceptibility zones and on existing deep landslides 2. Avoid adding material (weight) to the tops of susceptible slopes or, conversely 3. Avoid removing material from the bottoms of slopes (excavation or grading) Based on the applicant's May 14, 2019 supplemental report and Public Works referral comments dated July 29, 2019, the Planning Commission finds that the proposed development will follow recommendation #1 (control the input of water onto slopes within the moderate and deep landslide susceptibility zones and on existing deep landslide) by installing several detention systems to restrict the peak flow rate of the post-development conditions to a rate equal to or less than pre-development conditions (discussed further in Public Works Referral comments dated February 28, 2018). Once the runoff from the impervious surfaces has been detained via the detention systems, the runoff will be piped to a level spreader system located near the east boundary line of the proposed PUD. While several opponents have raised concerns related to this stormwater system, the Planning Commission finds that this proposal (in conjunction with Conditions of Approval 17 and 18) will mimic the existing conditions on the development site related to stormwater. The Planning Commission finds that a stormwater system that mimics existing site conditions should not result in any additional geologic risk to Final Order: Capital Hill PUD (PDT 17-1) Remand Page 7 the surrounding area. After reviewing the applicant's site plans Public Works staff determined that the applicant has not proposed excavation or grading at the bottom of slopes. See Public Works Referral Comments dated July 29, 2019. The Planning Commission therefore finds that the proposed development will follow recommendation #3 (avoid removing materials from the bottoms of slopes (excavation or grading)). Based on the evidence in the record, the Planning Commission finds that: 1) the PUD will utilize development techniques consistent with the recommendations included in the applicant's February 6, 2017 and May 14, 2019 Geotechnical Investigations that do not require removal mass at the base or toe of slopes; 2) the proposed PUD will utilize development techniques consistent with the recommendations included in the applicant's February 6, 2017 and May 14, 2019 Geotechnical Investigations that do not add mass to the top of slopes; and 3) consistent with the recommendations included in the applicant's February 6, 2017 and May 14, 2019 Geotechnical Investigations the proposed PUD includes a system that captures stormwater runoff from impervious surfaces and conveys that water to suitable points of disposal. The Planning Commission finds that the applicant has adequately considered on-site impacts of the proposed development and will implement recommendations designed to minimize those impacts. For all the reasons articulated above, as well as the reasons articulated in the Hearings Official's decision dated April 20, 2018, and the Planning Commission's Final Order dated June 14, 2018, the Planning Commission finds that the applicant's Geotechnical Investigations provide an adequate review of the on-site impacts of the proposed development and demonstrate that the proposed PUD will not create a significant risk to public health and safety through soil erosion or slope failure. Remand ;Issue' #2: Significant Risk to Public Health and Safety and Off-Site Impacts Final Order: Capital Hill PUD (PDT 17-1) Remand Page 8 LU A's Final pinion and Order Regarding the issue of off-site impacts of the development, LUBA explained: LUBA Final Opinion and Order dated November 20, 2018, LUBA Nos. 2018-074 and 2018-080, slip op at 39. Planning Commission's Determination: In response to this remand issue, the Planning Commission adopts the findings related to Remand Issue #1, above and adopts the following additional findings: The Planning Commission finds that off-site impacts of the development and the geologic risks to off-site public health and safety result primarily from stormwater run-off from impervious surfaces and potential landslides. As noted in response to Remand Issue #1, the Planning Commission finds that the proposed development will include installation of several detention systems to restrict the peak stormwater flow rate of the post-development conditions to a rate equal to or less than pre- development conditions (discussed further in Public Works Referral comments dated February 28, 2018). Once the runoff from the impervious surfaces has been detained via the detention systems, the runoff will be piped to a level spreader system located near the east boundary line of the proposed PUD. While several opponents have raised concerns related to this stormwater system, the Planning Commission finds that this proposal (in conjunction with Conditions of Approval 17 and 18) will mimic the existing conditions on the development site related to stormwater. The Planning Commission finds that a stormwater system that mimics existing site conditions should not result in any additional geologic risk to the surrounding area. In response to Remand Issue #1, the Planning Commission found that the applicant has adequately identified and will mitigate landslide risks on the subject site. The Planning Commission finds that mitigation of on-site landslide risks also necessarily mitigate risks of off- site landslide activity caused by the development. In addition, the applicant's May 14, 2019 Geotechnical Investigation outlines the various on-site and off-site investigations conducted by the applicant's geotechnical engineers, including off-site reconnaissance of the Floral Hill Drive area and the Ribbon Trail. The applicant's geotechnical experts did not observe any sign of Final Order: Capital Hill PUD (PDT 17-1) Remand Page 9 recent or on-going landslide activity. The applicant's May 14, 2019, Geotechnical Investigation concludes that: Opponents have raised issues of soil movement and point to an old barn on the subject Based on the evidence in the record, the Planning Commission agrees with the conclusion in the applicant's May 14, 2019 Geotechnical Investigation that landslide activity and associated off-site impacts are "best mitigated by incorporating the recommendations of [applicant's] February 6, 2017 report and the recommendations [from the applicant's May 14, 2019 Geotechnical Investigation] into the design and construction of the proposed development." As the Planning Commission found in response to Remand Issue #1, the PUD has incorporated the recommendations of the applicant's February 6, 2017 and May 14, 2019 Geotechnical Investigations as follows: 1) the PUD will utilize development techniques consistent with the recommendations included in the applicant's February 6, 2017 and May 14, 2019 Geotechnical Investigations that do not require the removal of materials at the base or toe of slopes; 2) the proposed PUD will utilize development techniques consistent with the recommendations included in the applicant's February 6, 2017 and May 14, 2019 Geotechnical Investigations that do not add mass to the top of slopes; and 3) consistent with the recommendations included in the applicant's February 6, 2017 and May 14, 2019 Geotechnical Investigations the proposed PUD includes a system that captures stormwater runoff from impervious surfaces and conveys that water to suitable points of disposal. The Planning Commission finds that the applicant has adequately considered off-site impacts of the proposed development and will implement recommendations designed to minimize those impacts. Additional Concerns Additional concerns submitted by interested parties include: ® Additional evidence of active slope movements ® Removal of existing trees will create geological hazard ® Applicant's site reconnaissance methods • The applicant's geotechnical report does not meet the criteria of a Level 3 Geotechnical Analysis Final Order: Capital Hill PUD (PDT 17-1) Remand Page 10 Active Slope Movements Interested parties raised concerns about soil movement on the steep eastern slopes of the PUD property, pointing to visual observations as well as testimony from neighbors who live downhill of the site along Floral Hill Drive. Several of these residents expressed concerns about flooding as well as foundational/structural issues stemming from active soil movements Removal of Existing Trees Interested parties submitted testimony arguing that the removal of established vegetation will decrease soil stability and will potentially increase the likelihood of a landslide. However, the applicant has demonstrated that removal of trees will only happen in areas of development, which are largely proposed within the flattest areas of the site. No trees are proposed to be removed within the conservation area along the east side of the site (with the exception of any removal authorized between Lots 13 and 14 by Condition of Approval #6 related to the storm sewer system), which is the area of the site with the highest landslide susceptibility. Site Reconnaissance Interested parties submitted testimony criticizing the reconnaissance methods used by the applicant to obtain observations and field geological data. The South Hills Study requires an "...adequate review of both on-site and off-site impact of any development by a qualified engineering geologist..." Mr. Gunnar Schlieder, Certified Engineering Geologist, concludes that since the applicant's licensed geologist was not in the field to conduct off-site work and reconnaissance, the applicant has not met the requirements of the South Hills Study. The Planning Commission disagrees with this conclusion. The applicant's engineering geologist signed and stamped the applicant's February 6, 2017 and May 14, 2019 geotechnical investigations. The Planning Commission finds that a geotechnical investigation that includes an adequate review of the on-site and off-site impact of a development and is signed and stamped by a licensed engineering geologist complies with the requirements of the South Hills Study. Level 3 Geotechnical Analysis Interested parties submitted testimony arguing that the May 14, 2019 geotechnical investigation provided by the applicant does not meet the requirements of a Level 3 Geotechnical analysis as outlined in EC 9.6710. The Planning Commission finds that this argument is moot because a Level 3 analysis is not required for this application. Final Order: Capital Hill PUD (PDT 17-1) Remand Page 11 EC 9.6710(3)(f) states: "The following activities are exempt from the requirements of this section:" "(f) Activities on land included on the city's acknowledged Goal 5 Inventory" safety through soil erosion or slope failure. For all the reasons articulated above, as well as the reasons articulated in the Hearings Official's decision dated April 20, 2018, and the Planning Commission's Final Order dated June 14, 2018, the Planning Commission finds that the applicant's Geotechnical Investigations provide an adequate review of the off-site impacts of the proposed development and demonstrate that the proposed PUD will not create a significant risk to public health and safety through soil erosion or slope failure. Remand Issue : Condition o Approval #1 LUBA's Final Opinion and Order In its April 20, 2018 Final Order, the Planning Commission modified Condition of Approval #10 adopted by the Hearings Official to require: A geotechnical analysis from a certified engineer, with specific recommendations for design and construction standards, shall be provided with any applications for Privately Engineered Public Improvement (PEPI) permits, as well as building permits and site development permits for the initial construction of infrastructure, and residences on individual lots. The development proposed with each permit shall adhere to the recommended standards for design and construction as contained in the preliminary geotechnical analysis approved for the tentative PUD, as well as any additional geotechnical analyses required for individual permits. The geotechnical analyses required for individual permits shall also address potential off-site impacts. LUBA's decision speculates in several places as to why the Planning Commission amended Condition of Approval #10. LUBA states: However, the planning commission seemed to recognize the incomplete nature of the Geotechnical Investigation in modifying Condition 10. Final Order: Capital Hill PUD (PDT 17-1) Remand Page 12 LUBA Final Opinion and Order dated November 20, 2018, LUBA Nos. 2018-074 and 2018-080, slip op at 38. LUBA Final Opinion and Order dated November 20, 2018, LUBA Nos. 2018-074 and 2018-080, slip op at 39. The apparent lack of evidence on this point [off-site impacts] may be the reason that the planning commission felt compelled to modify Condition of Approval 10, to require that all public improvements and building permits include a site- specific geotechnical analysis that addresses, among other things, "potential off- site impacts." LUBA Final Opinion and Order dated November 20, 2018, LUBA Nos. 2018-074 and 2018-080, slip op at 39-40. In the present case, however, the apparent lack of specific evidence and findings in the present record regarding off-site impacts suggests that the modification to Condition of Approval 10 was intended to overcome evidentiary insufficiencies in determining compliance with EC 9.8320(6) and 9.9630(3)(c). LUBA Final Opinion and Order dated November 20, 2018, LUBA Nos. 2018-074 and 2018-080, slip op at 40. Planning Commission's Determination For the reasons articulated above, the Planning Commission finds that the application complies with EC 9.8320(6) and the South Hills Study's specific recommendations for development standards related to review of on-site and off-site impact of the development. However, based on the understanding that this area is geologically-sensitive, and for the reasons outlined below, the Planning Commission also imposes the following Condition of Approval #110: A geotechnical analysis from a certified engineer, with specific recommendations for design and construction standards, shall be provided with any applications for Privately Engineered Public Improvement (PEPI) permits, as well as building permits and site development permits for the initial construction of infrastructure, and residences on individual lots. The development proposed with each permit shall adhere to the recommended standards for design and construction as contained in the applicant's geotechnical analyses dated February 6, 2017 and May 14, 2019. City Public Works staff has opined that the current industry practice is for a site-specific Final Order: Capital Hill PUD (PDT 17-1) Remand Page 13 The purpose of conditions of approval is to ensure that a proposed development which For the reasons articulated above, the Planning Commission finds that the approval criteria located in EC 9.8320(6) and the South Hills Study's specific recommendations for development standards related to review of on-site and off-site impact of the development are met without Condition of Approval #10. Therefore, the Planning Commission finds that imposition of Condition of Approval #10 does not defer a finding of compliance with applicable approval criteria to a subsequent building permit approval process that does not provide notice or public participation. Rather, the Planning Commission finds that Condition of Approval #10 as adopted in this Final Order will act as belt and suspenders to ensure that the individual improvements constructed on the site are constructed in a way that is geotechnically sound and that complies with the applicant's geotechnical analyses dated February 6, 2017 and May 14, 2019. V. CONCLUSION The Eugene Planning Commission has reviewed the record and has voted to affirm the decision to conditionally approve the tentative PUD for Capital Hill PUD (PDT 17-1). Additional findings and modified or added conditions of approval are provided in Section IV of this Final Order; all conditions of approval associated with this application are also included below for ease of reference. All conditions of approval, including conditions imposed by the Hearings Official, conditions imposed by the Planning Commission, and modified/replaced conditions remain applicable and are set out below. 1. The final PUD plans shall note that each single-family structure within the PUD shall provide for a minimum of two off-street parking spaces. 2. The final PUD plans shall replace "Notes" #2 on sheet L3.0 of the site plans with the following: Protective fencing for trees identified to be preserved shall be installed under the direction of a certified arborist and inspected and approved by the City prior to beginning any construction related activities. All protective tree fencing shall remain Final Order: Capital Hill PUD (PDT 17-1) Remand Page 14 in place until completion of all construction activities; any relocation or removal of the protective fencing shall also occur under the direction of a certified arborist, with approval by the City. 3. The final PUD plans shall replace "Notes" #3 on sheet L3.0 of the site plans with the following: 4. The final PUD plans shall remove "Notes" #9 on sheet L3.0 of the site plans. 5. The final PUD plans shall replace "Notes" #11 on sheet L3.0 of the site plans with the following: Trees in the common areas of Tract A and within individual lot preservation areas that die naturally or are damaged naturally and become potentially hazardous will require no replacement trees. The removal of dead, diseased, or hazardous trees is allowed with prior approval by a certified arborist and documentation of that approval (including the need for removal) provided to the City. 6. The final PUD plans shall replace "Notes" #13 on sheet L3.0 of the site plans with the following: Any trees to be removed in Tract A, as a result of installation of the storm sewer system between and near Lots 13 and 14, shall be replaced with two trees for every tree removed, after the City's acceptance of the system. Replacement trees shall be a native species, with a minimum caliper of 1 % inches for deciduous trees and a minimum height of 5 feet for coniferous trees and planted in the same general area. 7. For all lots that border Tracts A, B, C, and D or contain a preservation area, the final PUD plans shall include a temporary 10-foot construction setback area from all abutting preservation areas and Tracts A, B, C, and D. The following note shall be added to the final PUD plans: "For all lots that border Tracts A, B, C, and D or contain a preservation area, a temporary 10-foot construction area setback from all abutting preservation areas and Tracts A, B, C, and D shall be enforced during home construction, and shall include temporary construction fencing." 8. The final plans shall include a note that states the following: Final Order: Capital Hill PUD (PDT 17-1) Remand Page 15 9. The final PUD plans shall note that street tree removals must meet the permit and replacement value requirements of EC 6.305. 10. A geotechnical analysis from a certified engineer, with specific recommendations for design and construction standards, shall be provided with any applications for Privately Engineered Public Improvement (PEPI) permits, as well as building permits and site development permits for the initial construction of infrastructure and residences on individual lots. The development proposed with each permit shall adhere to the recommended standards for design and construction as contained in applicant's geotechnical analyses dated February 6, 2017 and May 14, 2019. 11. The final PUD plans shall include the following note: Lots 16 and 17 shall have the option of constructing up to three attached single- family structures. If only one single-family structure is proposed, that lot shall have a maximum lot coverage of 50% of the buildable portion of the lot. If two or three single-family structures are proposed, that lot shall have a maximum lot coverage of 65% of the buildable portion of the lot. The buildable portion of the lot shall be the area identified as outside any preservation area and shall not exceed 13,500 square feet, regardless of how many dwellings are developed on the lot. 12. The final PUD plans shall show a buildable area on Lots 5, 16 and 22 not to exceed 13,500 square feet. 13. Prior to final plat approval, the applicant shall provide documentation that EWEB has received a financial guarantee, in the form cash payment, bond, or an irrevocable letter of credit, ensuring water will be provided to each lot in the plat. 14. The final PUD plans shall revise the site plan Sheet C1- Wastewater and Water Plan to include 14-foot public utility or public wastewater easements, centered on the public wastewater mainlines, for all wastewater mainlines proposed on private property. In the event that a public mainline is proposed for location within 7 feet from the edge of a public right-of-way, a public utility or wastewater easement shall be dedicated on the adjacent private property at the width necessary to ensure 14 feet of operational and Final Order: Capital Hill PUD (PDT 17-1) Remand Page 16 maintenance access to the wastewater mainline (7 feet on each side), when combined with the public right-of-way within that 14 feet. 15. The final PUD plans shall revise the site plan Sheet C1- Wastewater and Water Plan to include wastewater services for Lots 18 - 19 that do not include private service lines within the public right-of-way. Private service lines may be relocated on private property, or public gravity service lines may be placed in the right of way. 16. The final PUD plans shall revise the site plans to include 5-foot sidewalks along the east side of Capital Drive. 17. The final PUD plans shall show that the stormwater runoff on the north and south ends of the additional Capital Drive road width will be treated through either filtration or mechanical treatment methods in compliance with the Public Improvement Design Standards manual. 18. The final PUD plans shall show that the stormwater runoff on the north and south ends of the proposed private street will be treated through a filtration facility in compliance with the Stormwater Management Manual. 19. Prior to final PUD approval, all requirements of EC 9.2750 Residential Zone Development Standards, including Table 9.2750 and EC 9.2751 Special Development Standards for Table 9.750, shall be met regarding the existing structure located on Lots 33 and 34. 20. The Written Owner Commitment to Fund Water Infrastructure executed by the applicant shall be re-executed to clarify that the Commitment applies to the entire subject property, including Tax Lot 201. 21. Prior to occupancy of any new dwellings in the PUD, applicant shall improve that section of Capital Drive abutting Lots 18 and 19, to ensure at least 21 feet of paving width within the existing right-of-way. The applicant shall also improve that section of Capital Drive abutting Lots 18 and 19 with a minimum 5-foot wide curbside sidewalk along the edge of Capital Drive abutting Lots 18 and 19 and within the existing right-of-way. The applicant shall obtain approval of a Privately Engineered Public Improvement permit for these required street improvements and provide documentation of compliance upon completion. 22. The final PUD plans shall include the following note: The maximum lot coverage for all lots is 50%. The square footage of any preservation areas shall be excluded in the calculation of lot coverage. Accordingly, the PUD is hereby approved with conditions. The foregoing findings and conclusions are adopted as the Final Order of the Eugene Planning Commission on Appeal of the Hearings Official's Tentative Approval for Capital Hill PUD (PDT 17-1), on this 13th day of August, 2019. Final Order: Capital Hill PUD (PDT 17-1) Remand Page 17 Kristen Ta , Chair Eugene Planning Commission Attachment A: Planning Commission Final Order, dated June 14, 2018 Attachment B: Hearings Official's Decision, dated April 20, 2018 Final Order: Capital Hill PUD (PDT 17-1) Remand Page 18