HomeMy WebLinkAboutApplicant Revised Final Argument (3-20-17)LAW OFFICE OF BILL KLOOS PC OREGON LAND USE LAW 375 W. 4T" AVENUE, SUITE 204 EUGENE, OR 97401 TEL: 541.343.8596 WEB: WWW.LANDUSEOREGON.COM March 17, 2017 Mr. Fred Wilson Eugene Hearing Official c/o Eugene Planning and Development Atrium Building 99 West 10th Ave. Eugene, OR 97401 Re: Amazon Corner TIA Appeal (City File TIA 16-7) Applicant Final Argument Dear Mr. Wilson: BILL KLOOS B I LLKLOOS@LANDUSEOREGON.COM Please accept this letter into the record as the applicant's Final Argument. This letter is intended to include argument only, and, if the Hearing Official determines that any contents of this letter constitutes new evidence, the applicant requests that such evidence not be considered. To summarize: This appeal is about compliance with a Rule that should not be applied at all, because the code states this use is a permitted use, not a.use that might be permitted depending on how someone might subjectively evaluate the mitigation of traffic impacts from the bit of traffic this will produce. Furthermore, the Rule can't be applied because the City has chosen not to make it a land use regulation, and it does not become a land use regulation just because it gets an honorable mention in the TIA section of the code. It is also not a land use regulation because it only involves information requirements; it is not listed as a substantive standard. Finally, when a TIA is done, the City traffic professionals have broad discretion, based on their technical expertise, to tailor the information requirements to the site and the task at hand. They did that and reduced the needed information to a homework assignment. The applicant turned that homework assignment in to the City experts and got and "A" grade. This is a highly technical process and product. The opponents should have a very, very high burden to discredit either the scope of the homework assignment or what was turned in. This argument is organized around the applicants' documents submitted at the hearing and during the seven and 14 day post-hearing submittal periods. We will use this letter as more of an outline that addresses issues, with reference made to parts of the documents we have already submitted. The hearing and post-hearing documents we have submitted are: Hearing documents: Mr. Fred Wilson March 17, 2017 Page 2 Sandow Engineering Technical Memorandum, 2.28, 2017 (responding to the information items included in Administrative Rule R-9.8650 (TIA Rule) and also attaching the Scope of Work agreement reached with the City of Eugene, Public Works Engineering) Lttr from Bill Kloos 2.27.2017 (regarding the pedigree of the TIA Rule) Seven day documents: Sandow Engineering Response to Transportation Issues 3.8.2017 (Record PDF page 2) Sandow Engineering Response to Lttr from Access Engineering 3.8.2017 (Record PDF page 9) Sandow Engineering Response to Items/Issues Raised at Hearing 3.8.2017 (Record PDF page 14) Lttr from Bill Kloos 3.8.2017 (relationship of TIA to "permitted use") (Record PDF page 22) 14 day documents: Jon Lauch Lttr responding to March 8 Staff Report, 3.10.2017 (Record PDF page 2) Jon Lauch email on bus "Bump-out" issue, 3.15.2017 (Record PDF page 15) Sandow Engineering Response to March 8 Attorney Mittge Lttr 3.15.2017 (Record PDF page 21) Sandow Engineering Response to March 7 Collinge Letter 3.15.2017 (Record PDF page 41) A. Procedural Issues The applicant requests that some of the opposing testimony submitted during the 14-day open record period should be stricken because it is outside the scope of what is allowed at that time. The scope of the post-hearing submission at the 14-day mark is limited by statute. The statute is ORS 197.763(6)(c), which says: "If the hearings authority leaves the record open for additional written evidence, arguments or testimony, the record shall be left open for at least seven days. Any participant may file a written request with the local government for an opportunity Mr. Fred Wilson March 17, 2017 Page 3 to respond to new evidence submitted during the period the record was left open. If such a request is filed, the hearings authority shall reopen the record pursuant to subsection (7) of this section." (emphasis added) Thus, between the seven day period and the 14 day period, a person may submit evidence responding to evidence submitted during the first seven day period. That is not a time to submit evidence responding anything submitted prior to or at the hearing. It is also not a time to submit evidence responding to anything that was submitted early during the second seven day period. All or part of three submissions by opponents on the 14a' day violate this limitation and should be stricken or disregarded. The 14 day submission by James Brock should be stricken, with the exception of the third paragraph on page one. That single paragraph responds to the seven day submission of Sandow Engineering; hence it is in the scope of what is allowed in the second seven day period. The balance is all material that could have been submitted at the hearing or in the first seven day submittal, or includes new evidence that is not allowed. The 14-day submittal by Mr. Fodor, dated March 15, also contains material that should be stricken. Section 5 on page 6 of this document contains material that should been submitted at the hearing. It is not responsive to any seven day submittal. The 14 day submittal of Mr. Collinge dated March 15 should be stricken because it is responsive to the 14 day submittal of Jon Lauch, which was dated March 15. A 14-day submittal filed early cannot be the target of another party's 14-day submittal. B. Substantive Issues There should be an order to this decision that starts at a pretty high level and then, in answering a series of questions, eventually moves down into the detailed nuances of traffic engineering. The applicant believes the inquiry should end at a fairly high level, with the Hearing Official affirming the Director's decision. The logical order of the questions should be: 1. Is a TIA requirement relevant to allowing this use, which is permitted outright by the code? 2. If the TIA approval is required to allow this use: (a) Is the City prohibited from applying the TIA Rule it because it is not an acknowledged land use regulation? (b) Is the TIA Rule a source of substantive standards for this decision, or is it just an information requirement that is not relevant at this juncture? Mr. Fred Wilson March 17, 2017 Page 4 3. If the TIA Rule information requirements can be applied at this juncture in the decision process, are the items of information alleged to be missing in the TIA report necessary to approve the report? 4. Is the TIA Report otherwise adequate on the merits? 1. The TIA requirement in the code is not relevant to allowing the proposed use, which is permitted outright by the code. This issue is the subject of the seven day submittal (March 8) from this office. Our March 8 memorandum explains that the uses proposed for this site are permitted outright or permitted subject to development standards, which have been met in the proposal. No party has argued otherwise. We summarize this point at page 2 of our March 8 letter: "To summarize, there is no explicit linkage in the code that makes this permitted use contingent upon complying with any substantive standard in the TIA process. If the TIA were intended to be a standard that limits the initiation of the use, state law requires that to be explicit in the code. ORS 227.173(1). We start with the premise that the zoning code lists the proposed uses as permitted uses, with the residential being subject to identified special development standards in EC 9.5000. The TIA requirement is not a "Special Development Standard" in EC 9.5000. Neither is it a "General Development Standard" in EC 9.6000. It is, instead, grouped with "Application Requirements and Criteria" in EC 9.8000." The TIA requirement in the code is inherently a discretionary review process; it involves judgments; it is processed as a statutory permit - hence the opportunity for appeal and a hearing. If the TIA process is viewed as a process that can potentially limit or block the proposed uses, that would transform a permitted use into a discretionary use, say a "conditional use," and that would be flatly contrary to what the code allows on this site as "permitted." 2(a) If the TIA review process is required to allow this use, then the City is prohibited from applying the TIA Rule because the Rule is not an acknowledged land use regulation. The entirety of opponents' objections to this application relate to compliance with the details of the TIA Rule. If the Rule is not a source of standards that may be applied by the City, then the objections of the opponents do not provide a basis for overturning the Director's approval of the TIA. This issue was discussed in depth in the hearing letter from this office dated February 27. Part 3(b) of our hearing letter documents the status of the Rule as not being acknowledged. It summarizes the Davenport and Von Lubken line of cases that explain that the City may only apply "land use regulations," and a local enactment only achieves the status of a land use regulation when it is acknowledged. Here we do not have a "land use regulation" because the Rule was not acknowledged. The City knows how to pursue acknowledgment of administrative Mr. Fred Wilson March 17, 2017 Page 5 rules. Our hearing memorandum documents the city's experience with its storm water rule, which it has taken through the acknowledgment process twice. Our hearing letter also explains that the TIA Rule does not acquire "land use regulation" status merely be being referenced in the text of the zoning code that was adopted before the Rule was adopted. The City has elected not to have the TIA Rule acknowledged. The City may shift gears and pursue acknowledgment in the future. However, at this juncture the City may not apply the Rule as a substantive standard in this proceeding because it is not a "land use regulation" in the meaning of ORS Chapter 197. 2(b). If the TIA process is required to allow this use, then the TIA Rule is not a source of substantive standards for this decision; it is just an information requirement that is not relevant at this juncture. Allegations of missing information are not a basis for a finding of noncompliance with the substantive standards. Information requirements are not approval standards. It is important to distinguish between information requirements and substantive standards for review. The former are needed to get an application in the door at the City and in the review process. The latter are applied to approve or deny the application. The TIA Rule has utility in helping the city professional staff to exercise their professional judgment in setting the scope of work for the TIA. The rule is not a basis for non-experts to second guess the judgment of the city professionals. This point is elaborated upon in item 2 of our February 27 hearing letter. Generally, allegations of missing information in an application are not a basis for remanding a decision or denying an application under the substantive standards that apply. Our hearing letter tracks the case law on this point, including a case involving the appellant Southeast Neighbors. The Hearing Official should find, categorically, that the TIA Rule is all about information requirements for the TIA; it is not a source of substantive standards that may be invoked to reject a TIA as inadequate. 3. The scope of the TIA was adequate under the code and the TIA Rule. Items of information alleged to be needed by the Rule but missing in the scope of work are not needed because they are "excepted" under EC 9.8675 and R-9.8650-E. The code and the TIA Rule recognize that setting the scope of work for a TIA is not a "one size fits all" exercise. The Rule states a very long list of information is potentially needed to be collected in a TIA. But the code and the Rule also allow the professional city staff to shrink the list a bit, based on the circumstances. This is what the City staff did here, and they were fully authorized to do so. This is more fully explained in item 1 of our February 27 hearing letter. Opponents took issue with the smallest details of what was and was not included in the TIA, disregarding the professional expertise and judgement of the technical experts City Engineers Mr. Fred Wilson March 17, 2017 Page 6 and Applicant Engineers. The applicant's traffic engineer walked through all the fine points of the information requirements stated in the TIA Rule, and explained, in much greater detail, why information that was not gathered for submission was not needed for the TIA. See Sandow Engineering's Technical Memorandum, February 28, 2017. As we mentioned at the hearing, with the aid of the small, medium and large "bucket" metaphor, this entire proceeding is about highly technical engineering information. The persons with large buckets of relevant technical information can be counted on just a couple of fingers, and they do not include the Hearing Official. Unlike the vast majority of land use decisions that hit the public hearing docket, this is the kind of inquiry in which the Hearing Official should be most deferential to the professional opinions of the City staff. Opponents had a long list of information critiques of the scope of work. Without getting too deep into the weeds, we would make the following several points about why the scope of work approved by the City and executed faithfully by Sandow Engineering was adequate: Intersections studied: Study area intersections are determined based upon 3 criteria; direct access, contiguous to the development, and development adds 50 new trips. The site driveways, Hilyard/32"a, Hilyard/31 St, and Hilyard/3 0 th ~ meet the above for warranting an analysis. All other intersections within the neighborhood do not meet the criteria for warranting an evaluation, therefore, they are not required to be included. Sandow Engineering's engineers and the City of Eugene's engineers used their technical expertise and professional industry standards to define how the study area meets the requirements. The arbitrary assertion that other intersections need to be studied based on proximity are well beyond the requirements of the code and in misalignment with the professional expertise and judgement of the engineers. Time periods studied: The site driveways are the only direct access to the development; therefore, they were analyzed for the AM and PM peak hours. Hilyard/ 32"d is the only contiguous (along the development frontage) intersection to the development; therefore, was analyzed for the AM and PM peak hours. Hilyard/3I" and Hilyard/300' had 50 trips added during the PM only, therefore they were included in the PM analysis. All other intersections within the neighborhood do not meet the criteria for warranting an evaluation. Intersection Performance and Mitigation: Sandow Engineering provided intersection LOS analysis for the PM and the AM conditions as required, contrary to assertion of Appellant's statements made up to and including the March 15th submittals. The LOS analysis as provided by the Applicant's engineer and approved by the City's engineer demonstrates that the mitigation, as described in the TIA and conditioned by the City, is sufficient to mitigate the impact of the development to City of Eugene's standards, and no other mitigation is necessary to meet the standards. Mr. Fred Wilson March 17, 2017 Page 7 The Hearing Official should find that the Director did not error in setting the scope of work for the TIA to include what was requested of the applicant, and to except the balance of the potential information requirements that were deemed unnecessary or irrelevant to inform the results of the analysis. 4. The TIA report was adequate to the task, and the Director's approval should be affirmed. We recommend to the Hearing Official, the Staff Report for the hearing, and the supplemental staff reports at the seven and 14 day periods. These reports address the major issues in good fashion. We note that the Staff has not addressed our arguments in points 1 and 2 above. That is understandable, as to do so would mean that the staff would be questioning the applicability of their own code language, which on the face of things would seem to apply. The applicant believes, however, that the points in 1 and 2 above are really threshold legal issues that should be in a first and second step, before getting to challenges to the adequacy of the TIA report. Here we address, in summary fashion, a handful of the more contentious issues that arose in the hearing and post-hearing periods. Each of these issues is addressed in detail in the applicant's documents listed above. (a) The appellant asserts that the TIA did not sufficiently address intersections beyond those that are contiguous to the site, that provide direct access to the site, and that are impacted by an additional 50 trips or more. The evidence in the record clearly demonstrates compliance in this regard. Two driveways provide the only direct access to/from the site to/from the adjacent streets; the intersection of 32nd & Hilyard is the only contiguous intersection; and only the intersections at 31" and Hilyard and 30°i & Hilyard are impacted by 50 trips or more. Analysis of all has been included in TIA. Broadening the study to analyze additional intersections in the wider neighborhood is not required, and it would not change the conclusions of the analysis. (b) The appellant has repeatedly claimed that an AM peak hour analysis has not been done. Actually, the Applicant has done this twice, using different approaches to the trip generation for the commercial retail space. See Sandow Engineering Letter to Scott Gillespie, December 26, 2017, and Sandow Engineering Response to Transportation Issues, March 8, 2017. (c) Lastly, the Appellant has alleged that the parking issue was not fully addressed. This has been addressed in detail in the Sandow Engineering's Response to Additional Testimony, March 15, 2017. Mr. Fred Wilson March 17, 2017 Page 8 In summary, the Applicant has provided a Traffic Impact Analysis that meets or exceed all City of Eugene standards and requirements, and we believe you should find in favor of Planning Director's original approval of the TIA for this development. Sincerely, Bill Kloos Bill Kloos Cc: Zach Mittge